Compliance Requirements for Gas Station
in ICAD Industrial City

Full step-by-step guide with costs, timeline and government authorities

9 steps
Steps
30,000–80,000 AED
Cost
60–120 days
Duration
5 authorities
Authorities
ℹ️

This is the general path for this facility type, not a path specific to ICAD Industrial City. The core requirements are the same, but the authority or the zone operator may add local conditions — confirm them before you proceed.

Compliance Roadmap — Step by Step

1

📋 Petrol Station Licence from ADDED

ADDED
2

MOIAT Storage Approval

MOIAT
3

🏅 Structural Requirements Compliance Certificate

Municipality
4

📐 Fire Safety Drawings for Petrol Stations

Municipality
5

📝 Hassantuk System Registration

Hassantuk
6

🔧 Foam Suppression System Installation — Specialist Class B

ADCDA
7

👷 Fuel Emergency Evacuation Plan

ADCDA
8

🤝 Annual Maintenance Contract with Certified Safety Company

ADCDA
9

ADCDA Civil Defence Certificate for Petrol Stations

ADCDA