Compliance Requirements for Print Shop
in ICAD Industrial City
Full step-by-step guide with costs, timeline and government authorities
9 steps
Steps
7,000–18,000 AED
Cost
35–65 days
Duration
4 authorities
Authorities
ℹ️
This is the general path for this facility type, not a path specific to ICAD Industrial City. The core requirements are the same, but the authority or the zone operator may add local conditions — confirm them before you proceed.
Government Authorities
Compliance Roadmap — Step by Step
1
📋 Industrial or Trade Licence from ADDED
ADDED2
✅ Media & Publications Authority Approval
Media3
🔧 Fire Alarm Installation — Class A
ADCDA4
👷 Adequate Ventilation for Inks & Solvents
Municipality5
🔧 Approved Chemical Fire Extinguishers
ADCDA6
✅ Civil Defence Approval
ADCDA7
✅ Load Demand Notification (LDN) with the distribution company
TAQA8
✅ Electricity connection approval and connection agreement
TAQA9
🔧 Electrical installation, testing and commissioning
DoERelated pages
Same facility, other zones
Other facilities, same zone
Hotel / Serviced Apt — ICAD Industrial CityUniversity / College — ICAD Industrial CityMall / Shopping Center — ICAD Industrial CityHospital / Medical Center — ICAD Industrial CityVilla / Private House — ICAD Industrial CityResidential Building — ICAD Industrial CityFactory / Industrial — ICAD Industrial CityPharmacy / Medicine Store — ICAD Industrial CityWarehouse / Storage — ICAD Industrial CityLogistics Center — ICAD Industrial City