Government Authorities

Compliance Roadmap — Step by Step

1

📋 Trade Licence & Shopping Centre Licence

ADDED
2

🏅 Building Completion Certificate & Requirements Compliance

Municipality
3

📐 Approved Safety & Evacuation Drawings from Engineering Consultant

Municipality
4

📝 Hassantuk System Registration — Corporate Level

Hassantuk
5

🔧 Alarm, Suppression & Water Sprinkler System — Class A+B

ADCDA
6

👷 Emergency Team Training & Approved Evacuation Plan

ADCDA
7

🤝 Periodic Maintenance Contracts with Certified Safety Companies

ADCDA
8

Comprehensive Inspection & Civil Defence Certificate

ADCDA
9

Load Demand Notification (LDN) with the distribution company

TAQA
10

Electricity connection approval and connection agreement

TAQA
11

🔧 Electrical installation, testing and commissioning

DoE