Compliance Requirements for Factory / Industrial
in ADGM Free Zone

Full step-by-step guide with costs, timeline and government authorities

11 steps
Steps
25,000–80,000 AED
Cost
90–180 days
Duration
6 authorities
Authorities
ℹ️

This is the general path for this facility type, not a path specific to ADGM Free Zone. The core requirements are the same, but the authority or the zone operator may add local conditions — confirm them before you proceed.

Government Authorities

Compliance Roadmap — Step by Step

1

📝 Industrial Registry Issuance from MOIAT

MOIAT
2

📋 Industrial Licence from ADDED

ADDED
3

Environmental Approval from EAD

EAD
4

🔧 Full Fire System Installation — Class A + B + E

ADCDA
5

📝 Hassantuk System Registration

Hassantuk
6

📐 Approved As-Built Drawings

Municipality
7

👷 Appointment of Occupational Health & Safety Officer

MOHRE
8

Final ADCDA Civil Defence Approval

ADCDA
9

Load Demand Notification (LDN) with the distribution company

TAQA
10

Electricity connection approval and connection agreement

TAQA
11

🔧 Electrical installation, testing and commissioning

DoE