In Abu Dhabi, temporary traffic signs at road works fall under the traffic sign manual TR-511 (4th edition, June 2024) and the Work Zone Traffic Management Manual TR-531 (3rd edition, October 2020). TR-511 calls for a yellow ground with black legend and border on road-works signs, ASTM D4956 Type IV reflective sheeting on regulatory and warning signs (Type XI on overhead signs), and sign sizes that rise with the road's design speed. TR-531, which sets work-zone layouts and device spacing, is not public, so its detail is not reproduced here. Leaving temporary signs on the road after the works is a violation on the ITC schedule (AED 5,000 in the 2020 procedures manual; ITC announced an updated schedule on 28 January 2026, so confirm the current amount with ITC). Dubai works from a different document, the Dubai Municipality construction safety code.
What the code requires
| Requirement | Source | Applies in |
|---|---|---|
| Road-works signs: yellow ground, black legend and border (regulatory signs such as speed limits are excepted) | TR-511, Table 4-9 | Abu Dhabi |
| ASTM D4956 Type IV reflective sheeting for regulatory and warning signs; Type XI for overhead and coloured guide signs | TR-511, §1.26.8.3 | Abu Dhabi |
| Maintained retroreflectivity: yellow at least 100 and red at least 30 cd/lx/m²; contrast at least 3:1 | TR-511, Table 4-5 | Abu Dhabi |
| Warning triangle (side length) by design speed: 750 mm up to 40 km/h, 900 mm at 60, 900–1200 at 80, 1200–1500 at 100, 1500 mm at 120 km/h and above | TR-511, Table 4-8 (minimum recommended sizes for ground-mounted signs; the higher figure applies on the more important road in the band) | Abu Dhabi |
| Regulatory circle: 600 mm up to 40 km/h, 750 at 60, 750–900 at 80, 1200 mm at 100 and at 120 km/h and above | TR-511, Table 4-8 | Abu Dhabi |
| Diagrammatic sign (W × H): 900 × 1200 mm up to 40 km/h, 1200 × 1600 at 60 and 80, 1800 × 2400 at 100, 2250 × 3000 mm at 120 km/h and above | TR-511, Table 4-8 | Abu Dhabi |
| Urban mounting: bottom edge 2100–2500 mm above ground, 450–1000 mm from the edge of an arterial or local road | TR-511, Table 4-10 | Abu Dhabi |
| Barricades red and white, reflective; cones at least 450 mm high | TR-511, §1.33.10 | Abu Dhabi |
| Work-zone layouts, devices and spacing for each type of work zone; binding on all entities by Executive Council resolution | Work Zone Traffic Management Manual TR-531 (3rd ed., October 2020) — not public | Abu Dhabi |
| Schedule of violations (2020): AED 5,000 for failing to remove all temporary signs, markings, equipment and debris from the right-of-way during or after the works; AED 100,000 for works without a detour permit; AED 50,000 for deep excavation without barriers. Note: ITC announced an updated schedule of violations and fines on 28 January 2026 and we could not find the updated amounts published, so confirm the current figure with ITC | ITC detour procedures manual (2020), Appendix 1, and ITC announcement of 28 January 2026 | Abu Dhabi |
| Barricades with reflective banners at 45° to the direction of travel, red/white or yellow/black | DM Code of Construction Safety Practice §6.1.4 | Dubai only |
| STOP/SLOW paddle: 450 mm octagon on a 1.2 m pole; STOP in high-intensity reflective red with letters at least 150 mm; SLOW in black on a reflective yellow diamond with letters at least 120 mm | DM Code of Construction Safety Practice §6.5.1 and Chapter 20 | Dubai only |
| Flashing amber lights at night | DM Code of Construction Safety Practice | Dubai only |
| Not specified in the sources: any temporary traffic sign rule for the other emirates; the detail of TR-531 (not public); a paddle specification for Abu Dhabi; which party is fined | No text in the cited sources | — |
If you need these items produced, work-zone signs, barricade boards and paddles for road works are made to the project's approved traffic management drawing; the requirements above apply whichever supplier you use.
Who is responsible
TR-531 is stated to be binding on all entities by Executive Council resolution, but the sources used here do not name which party each fine is directed at (contractor, owner or permit holder), nor who prepares or signs the traffic management plan. Check the detour permit conditions, the project contract and TR-531 itself with the issuing authority rather than assuming.
What an inspection against these clauses looks at
- Colour of road-works signs: yellow ground, black legend and border (Table 4-9).
- Type of reflective sheeting: Type IV for regulatory and warning signs, Type XI for overhead signs (§1.26.8.3).
- Each sign's size against the road's design speed (Table 4-8).
- Whether retroreflectivity and contrast remain within the stated values in service (Table 4-5).
- Mounting height and offset from the road edge (Table 4-10).
- Red and white reflective barricades, and cone height (§1.33.10).
- Whether the work-zone layout matches the TR-531 layout approved in the permit.
- Whether all temporary signs, equipment and debris are removed once the works end (ITC Appendix 1).
- In Dubai: banner angle of 45°, night lighting, and the paddle size and lettering (§6.1.4 and §6.5.1).
Typical gaps against the requirement
- A white or orange ground on a road-works sign instead of yellow — against Table 4-9.
- Sheeting of a lower class than Type IV on a regulatory or warning sign — against §1.26.8.3.
- A sign size chosen by habit rather than by design speed — against Table 4-8.
- A sign that has lost reflectivity or contrast through use and exposure — against Table 4-5.
- Signs mounted lower, nearer or further from the road edge than the stated values — against Table 4-10.
- Temporary signs, markings, equipment or debris left on the road after the works — against the ITC procedures (AED 5,000 per the 2020 schedule).
- Works started without a detour permit (AED 100,000 per the 2020 schedule) or deep excavation without barriers (AED 50,000 per the 2020 schedule) — against Appendix 1.
- Applying the Dubai 450 mm paddle figures to an Abu Dhabi project — they come from the Dubai code, not TR-511.
The fine amounts above are the only ones the sources state; no enforcement frequency or statistics are given. On site, these temporary signs sit alongside the on-site safety signs that go with them, which are governed by different requirements not covered on this page.
Checklist
- ☐ I hold the traffic management plan and the detour permit, and have asked the issuing authority for TR-531 because it is not public.
- ☐ Road-works signs have a yellow ground with black legend and border (Table 4-9).
- ☐ Reflective sheeting is ASTM D4956 Type IV for regulatory and warning signs, Type XI for overhead (§1.26.8.3).
- ☐ I have recorded each road's design speed and chosen the matching sign size (Table 4-8).
- ☐ Retroreflectivity (yellow at least 100, red at least 30) and 3:1 contrast are checked on signs in use (Table 4-5).
- ☐ Urban signs are mounted with the bottom edge at 2100–2500 mm and 450–1000 mm from the road edge (Table 4-10).
- ☐ Barricades are red and white reflective and cones are at least 450 mm (§1.33.10).
- ☐ Abu Dhabi: no work started before the detour permit was issued (Appendix 1).
- ☐ Any deep excavation is protected by barriers (Appendix 1).
- ☐ A removal plan covers all temporary signs, equipment and debris at the end of the works (Appendix 1).
- ☐ Dubai: barricade banners at 45°, paddle 450 mm on a 1.2 m pole (§6.1.4 and §6.5.1).
FAQ
What colour are temporary road-works signs in Abu Dhabi?
A yellow ground with black legend and border, except regulatory signs such as speed limits, under TR-511 Table 4-9.
How large must a road-works warning triangle be?
It depends on design speed in TR-511 Table 4-8: 750 mm per side up to 40 km/h, 900 mm at 60, 900–1200 mm at 80, 1200–1500 mm at 100 and 1500 mm at 120 km/h and above. The higher figure in a band is for the more important road.
Which reflective sheeting is required?
TR-511 §1.26.8.3 specifies ASTM D4956 Type IV for regulatory and warning signs and Type XI for overhead and coloured guide signs. Any project-specific grade sits in the work-zone documents; TR-531 is not public.
What is the fine for leaving temporary signs after the works?
Per Appendix 1 of the ITC detour procedures manual (2020): AED 5,000 for failing to remove all temporary signs, markings, equipment and debris from the right-of-way during or after the works and before the road reopens, AED 100,000 for works without a detour permit, and AED 50,000 for deep excavation without barriers. ITC announced an updated schedule of violations and fines on 28 January 2026 and we could not find the updated amounts published, so check the current figure with ITC.
Do the STOP/SLOW paddle dimensions apply in Abu Dhabi?
That cannot be confirmed. The 450 mm octagon on a 1.2 m pole and the 150 mm and 120 mm lettering come from the Dubai Municipality code, and the sources used here give no matching Abu Dhabi specification. Check TR-531 and your permit conditions.
Looking for a supplier for these signs — or want to have them printed?
Art for Printing is our trusted printing and signage partner in the UAE for site signage: it produces work-zone signs, barricade boards and STOP/SLOW paddles for road works.
Disclosure: Art for Printing is independent of SafePass. SafePass has a marketing agreement with it to direct readers who need printing. This is a commercial referral, not an approval or certification by ADPHC or any authority, and the requirements above apply whichever supplier you use.