Compliance Requirements for Logistics Center
in Khalifa City A & B
Full step-by-step guide with costs, timeline and government authorities
9 steps
Steps
15,000–40,000 AED
Cost
60–120 days
Duration
4 authorities
Authorities
ℹ️
This is the general path for this facility type, not a path specific to Khalifa City A & B. The core requirements are the same, but the authority or the zone operator may add local conditions — confirm them before you proceed.
Compliance Roadmap — Step by Step
1
📋 Logistics Licence from ADDED
ADDED2
✅ Department of Transport Approval
DoT3
🔧 Warehouse Fire System — Class A + E
ADCDA4
📝 Hassantuk Registration & Monitoring Systems
Hassantuk5
🪪 Shipping & Storage Permits
ADDED6
✅ ADCDA Civil Defence Approval
ADCDA7
✅ Load Demand Notification (LDN) with the distribution company
TAQA8
✅ Electricity connection approval and connection agreement
TAQA9
🔧 Electrical installation, testing and commissioning
DoERelated pages
Same facility, other zones
Logistics Center — Abu Dhabi IslandLogistics Center — Abu Dhabi MainlandLogistics Center — Musaffah IndustrialLogistics Center — ICAD Industrial CityLogistics Center — KIZAD Khalifa IndustrialLogistics Center — Reem IslandLogistics Center — Saadiyat IslandLogistics Center — Yas IslandLogistics Center — Al Ain CityLogistics Center — Al Ain Industrial
Other facilities, same zone
Hotel / Serviced Apt — Khalifa City A & BUniversity / College — Khalifa City A & BMall / Shopping Center — Khalifa City A & BHospital / Medical Center — Khalifa City A & BVilla / Private House — Khalifa City A & BResidential Building — Khalifa City A & BFactory / Industrial — Khalifa City A & BPrint Shop — Khalifa City A & BPharmacy / Medicine Store — Khalifa City A & BWarehouse / Storage — Khalifa City A & B