What is FLS (Fire & Life Safety) approval?
FLS approval is the Abu Dhabi Civil Defence Authority (ADCDA) sign-off on a facility fire-protection and life-safety drawings. It is required before installing the systems and before a building completion certificate or licence renewal is issued. The review covers alarm, suppression, passive protection and emergency egress against the UAE Fire & Life Safety Code.
Approval steps
- Submit architectural and protection-system drawings through an ADCDA-registered consultant or contractor.
- Design review against the code and adopted NFPA standards.
- Design approval (No Objection Certificate), then execution.
- Submit As-Built drawings after installation.
- Field inspection, final approval and safety certificate issuance.
Required documents
- Municipality-approved architectural drawings.
- Protection-system drawings (alarm, sprinkler/suppression, pumps, emergency lighting) signed by a licensed engineer.
- Design calculations: sprinkler density, detector coverage, occupancy load and travel distances.
- Equipment specifications and approval certificates (UL/FM/EN).
- A documented maintenance contract from a certified company at operation.
Common rejection reasons
- Insufficient detector spacing or sprinkler coverage for the ceiling height and hazard class.
- Missing occupancy-load and travel-distance calculations.
- Water supply or pump room not compliant with NFPA 20.
- No Hassantuk connection where mandated.
- As-Built drawings inconsistent with the approved design.
Frequently Asked Questions
When is FLS approval required?
Before installing the protection systems and before a completion certificate or licence renewal; any material change to the systems requires re-approval.
How long does approval take?
It depends on drawing and calculation completeness and submission quality; a code-compliant first submission that avoids the rejection reasons above is the fastest route.
Can I submit it myself?
It is normally submitted through an ADCDA-registered consultant or contractor to ensure drawings and calculations meet the code.